Eyxeinoupolis Substation

Eyxeinoupolis Substation


LOCATION Almyros Municipality, Magnesia Prefecture, Greece
PROJECT TYPE Substation
LAND COVERAGE 11000 sqm
NOMINAL POWER 50.0MW
PROJECT STATUS Operational Since Οκτώβριος 2013
OWNERSHIP EuroEnergy

Overview


Substation Euxeinoupoli is located in Almyros Municipality, Magnisia Prefecture. The land where the substation is located is owned by EuroEnergy. Initially, it was equipped with a 20/150 KV, 50 MVA transformer, through which Mpozalo Solar project is connected to High Voltage, while a 100MVA transformer was added afterwards by a new participant.